PROGRESS UPDATE QUARTER 1, 2026

14 Apr 2026
J002535 OR1 Oranga Progress Update DEC Blog header 1600x800px 1IT

WHAT’S HAPPENING ON THE GROUND

The Oranga Development is well underway, transforming the area with warm, modern homes, safer streets and upgraded infrastructure. Over time, around 400 existing social homes will be replaced with approximately 1,300 new homes, including a mixture of social homes and homes to buy on the open market.

PROGRESS SO FAR

  • We're excited to see Elaman begin construction over summer on the corner of Olea Road and Oranga Avenue, delivering 25 architecturally designed terrace homes to the market. Interest has already been strong, so if you're keen to learn more, you can find the sales info here.

  • The Oranga Info Centre was decommissioned in February, but it's still easy to get in touch with the team. Just head to our  website for all the contact details.

LOOKING AHEAD

  • We are looking forward to the start of construction in April/May for 15 townhouses on Roosevelt Ave by Field Homes, with a sales campaign launching soon. 

  • From late May/June, nine additional homes are scheduled for demolition to make way for future development. Several new developers are currently exploring opportunities to deliver more market homes in Oranga.

  • We have also been working with several new developers who are exploring opportunities to deliver more market homes in Oranga. Watch this space for further updates!

TIMELINE

Autumn/Winter 2026

  • Design and consenting work is progressing well for the upcoming pathway upgrades, and Olea Road/Fergusson Park frontage upgrade. These enhancements will help create safer, more accessible routes for the community.

  • Continuing design and consenting for the new public wastewater extension through to Rockfield Road. 

Summer 2026/2027

  • Construction of 22 new social homes across 3 superlots will be underway.

  • Construction commences on the first pathways and Olea Road- Fergusson Park frontage.

COMPLETED HOMES

NEW HOMES

STAGE 1 STAGE 2 STAGE 3
SOCIAL 51 108 74
MARKET 0 0 135
TOTAL 51 108 209

* Approximate numbers only. We will provide updates if there are any changes to the plans.



YOU’RE INVITED - ORANGA NEIGHBOURS DAY!

Join us for a fun-filled day at Oranga Neighbours Day on Saturday, 17 April! Enjoy FREE activities for the whole whānau, including a kids’ market, plant swap, bouncy castle and more. Click here for all the details!

HOMES FOR SALE

From first homes to forever homes – there are all sorts of beautiful, brand new, high-quality houses for sale in Oranga Development. See all of the homes for sale right now, here.

WANT TO KNOW MORE?

Click here to learn more about Oranga Development or get in touch with the team.